How to estimate a concrete footing
A continuous footing is a long, narrow box. You measure the run one way and the width and depth another way. This guide shows that split, a few real volumes, and the mistakes that over-order. It does not say how deep your footing must be.
Length is not the width
People measure a wall in feet and the footing under it in inches. The concrete footing calculator is built for that habit. Length is the run, in feet or metres. Width and depth are the cross-section, in inches or millimetres. A 20 foot wall on a footing 16 inches wide and 8 inches deep is length 20, width 16, depth 8. If you type 16 in a field that expects feet, you have described a slab, not a trench.
The form rejects a width or depth above 48 inches, or 1,200 millimetres, and says the unit is probably wrong. That check exists because a 400 inch footing is usually 400 millimetres typed in the wrong mode. If you truly need something wider, you are likely pouring a slab, and the slab calculator is the form that expects both plan dimensions in the same unit.
Walk the foundation and list every straight run, including the short pieces and the jogs. An L is two lengths. A step down is two depths on two lengths. Add the bag counts or the volumes at the end. One “about 80 feet” that skips a corner shows up as a gap on pour day. Averaging two depths is fine only when you computed the average and wrote it down.
A box you can check by hand
Cubic feet are the length in feet times the width in inches times the depth in inches, divided by 144. Divide by 27 for cubic yards. A 20 foot run, 16 inches wide and 8 inches deep, with no waste, is 0.66 cubic yards. At 0.60 cubic feet per 80 lb bag that is 30 bags. The waste field on the form starts at 5 percent, so the live result is larger than this bare box unless you set waste to zero. The example uses zero so you can redo 20 × 16 × 8 ÷ 144 without a hidden allowance.
A longer trench, 40 feet by 24 inches by 12 inches with 10 percent waste, is 2.96 cubic yards exactly and 3.26 cubic yards to order, which is 147 bags of 80 lb mix. The jump from 2.96 to 3.26 is the 10 percent. If the forms are tight, you may not want that much extra. Type the allowance you mean and read the count again before you buy.
In metres, 12 metres by 400 millimetres by 200 millimetres with 10 percent waste is 0.96 cubic metres exactly and 1.06 cubic metres to order, which is 88 bags at the 0.012 cubic metre planning yield for a 25 kg bag. The same yields are used on the slab and column pages: 0.60, 0.45, and 0.30 cubic feet for 80, 60, and 40 lb. They are typical dry-mix figures. The number on your bag replaces them.
Piers are not a trench
A round pier has a diameter and a height and a count. That is the concrete column calculator, not this trench. Four 12 inch piers, 8 feet tall, with no waste, are 0.93 cubic yards and 42 bags of 80 lb mix. One 16 inch square column, 8 feet tall, is 0.53 cubic yards and 24 bags. Six 300 millimetre piers, 2.4 metres tall, with 10 percent waste, are 1.02 cubic metres exactly, 1.12 to order, and 94 bags of 25 kg mix.
A pier sitting on a wider pad is two shapes. The pad might be a short footing or a small slab. The pier is the column page. Entering the pad width as the pier diameter orders a fat column and forgets that the pad is thinner than the pier is tall. Add the volumes. Do not average them into one pretend shape.
Depth on the footing page is the concrete in the trench. If you put gravel in the bottom and then pour concrete on top, the gravel is not part of this volume. Order the stone on its own. Using one depth for both counts the same hole twice or misses a material.
What the number is for
Small runs and a handful of piers are often bag jobs. A house perimeter is often ready-mix. Read the volume to order to the plant. Read the bag count only when you are buying bags, and read the yield line with it. The page does not know the plant’s minimum load or the price of the truck.
This guide will not tell you the footing size your soil or your climate requires. Frost depth, bearing, and the weight of the wall are local and specific. If a drawing or a permit already gives the width and the depth, type those. The examples are checks on the multiplication, not recommended sizes. Rebar, form boards, and whether the trench is on undisturbed ground are outside the volume.
Write the list of runs, the cross-section, and the waste you chose. Then compare the yield on the result with the bag in the store, or compare the cubic yards with the plant’s ticket. The patio guide is the other concrete shape, a flat rectangle, if the job is a slab rather than a wall.
Calculators for this job
- Concrete footing
Continuous footing from length, width, and depth, plus a bag count.
- Concrete column
Round or rectangular piers from the cross-section, height, and how many you are pouring.
Updated 29 November 2026. Written by August H. The byline is not a claim of a license or a trade.